Project : SETI-II SHP
Development Region : Gadaki pradesh
District : Kaski, Pokhara city
Water Source : Pokhara Irrigation Scheme
Type of Scheme : Irrigation Canal Drop (ROC)
Access Road to Head pond : 3 km from Kandahar, pokhara
Discharge of Seti Canal : 9.0 m 3/sec
Design Discharge Plant : 4.55m3/sec
Intake : Inlet gate to headpond near cross regulator
Location : 2 kulomuhan, Banjhapatan
Forebay : Headpond with spillway
Design WL at Forebay : 978.2m
Spillway Canal Existing Irrigation Canal: (807m)
Penstock Type : Mild Steel (1.9m dia) welded buried pipe
Length of Penstock : 732m
Powerhouse : Compact PH with inclined machine layout
Tailrace : Box Culvert with bypass system
Turbine ; 2 units Francis
Generator : 624kVA, 2units Synch AC 0.4kV
Transformer : One 0.4/11kV, 1275 kVA
Transmission : 11kV, 5.3 km.
Interconnection Point : NEA 132/11 kV, Khundahar Substion
Installed Capacity : 979 kW
Gross Head : 28.0 m
Deemed Energy : 6.98 GWh
PPA date : 08 Aswin 2063
Construction Started : Falgun 2063
CoD Date : 14 Falgun 2065
Cost of the Project with IDC : 17 core